Riverside's Fifth Plan and What It Means for Lower Falls and Auburndale

At the Newton City Council Land Use Committee meeting on Tuesday, November 10, Stephen Buchbinder told councilors he had worked on the Riverside site since 2009. He said he hoped that this time the project would actually be built. Buchbinder is an attorney for the petitioners. The 9.34 acres at 0, 355 and 399 Grove Street have been approved before, more than once, and each earlier plan stalled. Version five is now in front of the committee, and it is a different kind of neighbor for Newton Lower Falls and Auburndale than any version before it.

For a buyer looking at a house within walking distance of Riverside station, the main question has changed. Earlier plans left you guessing whether anything would ever be built. This plan has three development partners, an MBTA deadline, and a building program that, by the petitioner's own traffic count, puts fewer cars on Grove Street at rush hour than the plan the City Council approved last December.

Five versions on one site

Before 2026, every Riverside plan was a larger mixed-use project. A 2013 special permit came with rezoning of parts of the MBTA and Hotel Indigo parcels. The 2020 proposal had ten buildings with 582 homes, about 254,000 square feet of office space, a 150-room hotel and close to 39,000 square feet of ground-floor commercial space. A later version of it was approved in 2021. According to Fig City News, that plan stalled as construction costs and interest rates rose and demand for office and lab space weakened.

The plan approved in December 2025 dropped the hotel and nearly 370,000 square feet of office and lab space, as the Newton Beacon reported at the time. Here is how that approval compares with the amendment now before the committee:

Approved December 2025 Proposed November 2026
Total homes 753 711
Regular apartments 753 444
Assisted living and memory care units 0 267
Retail space About 20,000 sq ft Retained
Structured parking 980 spaces 727 spaces
Total parking 1,110 stalls 201 fewer

The rest of the site plan changes in smaller ways. The central green becomes fully pedestrian, the play space moves onto it, and the developers describe a safer walking connection down to the Charles River. The Newton Beacon's November 2 report says gardens replace the play area along Grove Street and will also help with stormwater. Project representatives also described connections to Riverside Park, the MWRA yards and the Charles, along with better bike routes.

Why this plan has a firmer calendar

The 2025 approval stalled on money. At the November 10 hearing, developer Robert Korff said all of the site's infrastructure has to be built first. He also said the roughly $600 million cost was too much for one company to carry, so the project was split into three separate financing structures. Greystar, the master developer, would own Buildings 1 and 6, the garage, and all on-site and off-site infrastructure. Harbert South Bay would own Buildings 2 and 3, and Mark Development would keep Buildings 4 and 5. In August, Fig City News reported that Mark Development had struggled to raise about $150 million on its own.

The MBTA deadline is the other new factor. Fig City News reported in August that the latest agreement with the MBTA requires construction to start by March 2027 and finish within four to five years. At the November 10 hearing, Buchbinder said the full City Council has to vote by early February to meet the MBTA's deadline, which he tied to the scheduled delivery of 102 new Green Line cars to Riverside. The Beacon's November 2 report says that if the amendment is approved, construction would begin next spring and take about four years.

By our own rough math, a spring 2027 start plus about four years would put finished buildings somewhere around 2031, and later if the work runs to five years. A family buying near Grove Street this winter should expect to live through most of that construction period. The questions worth asking are about those years: truck routes, where the walking paths run, and how the station operates while it is a work site.

Approval is still pending. The committee held the matter by a 7-0 vote and kept the public hearing open. An independent traffic peer review commissioned by the Planning Department is scheduled for the December 8 meeting, and another session is planned for mid-to-late January.

A lighter load on Grove Street, by the petitioner's count

The biggest change is in who lives in Buildings 2 and 3, the two buildings that, according to Fig City News, face Lower Falls. Lisbeth Tibbits-Nutt, the petitioner's transportation planner, told the committee that the average senior-living resident would be 82 to 95 years old and that few would own cars. She said the largest staff shift would be 68 employees, a shuttle would take residents off site, and peak senior-housing parking demand would be about 109 cars in a separate 152-space garage.

Randy Hart, the petitioner's traffic consultant, projected that the new mix would cut daily weekday traffic by 2%, morning peak traffic by 11% and evening peak traffic by 13% compared with the approved plan. He said the off-site roadway design with MassDOT is making progress. These are the developer's projections. The city's peer review on December 8 is the independent check on them.

Commuters who park at Riverside station, at 367 Grove Street, keep the same commitment as before. The MBTA still gets 650 spaces, with 286 in a dedicated surface lot and 364 in the Building 6 garage reserved for peak periods. Residential parking is planned at one space per apartment, with residents' demand peaking at night and the MBTA's during the day.

The housing mix also changes how affordable housing is handled. Because affordable assisted-living units are not practical, Mark Development plans a cash payment instead of on-site affordable units in the senior buildings. The city's analysis puts the payment at $4,355,000, split equally between the Newton Affordable Housing Trust and the Newton Housing Authority.

Councilors had questions of their own. They raised a possible 10 to 15% parking cushion, the scale of the buildings along Grove Street, the glass connector between Buildings 2 and 3, shuttle details, and asked for more three-bedroom units. One resident who spoke asked for evidence that the financing is committed. The amendment also adds height along Grove Street and lowers the parking garage. If you are looking at homes on the streets that face the site, check those elevations closely.

What Newton's price map says about the trade

Newton's assessors publish single-family sale prices by district, and the latest figures cover calendar year 2025. The median single-family sale in the Lower Falls district was $1,400,000, against $1,850,000 citywide. Auburndale's Islington and south-of-Commonwealth Avenue district had a median of $1,653,400, and the district combining Auburndale and West Newton north of the Pike came in at $1,630,000. Among Newton's single-family districts, only Upper Falls at $940,000 and Nonantum at $1,000,000 had lower 2025 medians than Lower Falls.

That $450,000 gap between Lower Falls and the citywide median in 2025 is the trade a buyer is making near Grove Street. On one side is a lower purchase price, a Green Line terminus and a road toward the Charles. On the other is a roughly four-year construction project next door if the spring 2027 start holds. With the senior-housing version, the buildings closest to Lower Falls would hold residents who, by the petitioner's count, rarely drive, instead of 309 market-rate apartments.

Citywide, buyers have more room to negotiate this fall than they did a year ago. In October 2026, Newton closed 54 sales, down from 81 in October 2025, according to the Boston Real Estate Observer's October report. The typical single-family home sold for $1.2 million after 21 days to an accepted offer, and the typical condo sold for $875,000. In October, 31% of Newton homes sold for their first asking price or more, compared with 44% in October 2025. The typical sale closed at 96.0% of first asking. Price per square foot in October was 10% lower than a year earlier, and 88 homes came on the market that month while 59 went under agreement.

Taken together, a buyer this winter is negotiating in a slower citywide market, in the village that already had one of Newton's lowest single-family medians in 2025, right before the council vote that decides whether construction starts in the spring. If you are still deciding between villages, our guide to Newton neighborhoods and housing styles covers how Lower Falls and Auburndale homes differ from the rest of the city. If you are weighing a condo against a house, see our post on condo or single-family in Newton.

FAQ

When would Riverside construction start?

The Newton Beacon reports that if the amended special permit is approved, construction would start next spring and take about four years. Fig City News reported that the MBTA agreement requires a start by March 2027.

Does commuter parking at Riverside station change?

Under the new plan, the 650-space MBTA commitment is unchanged, split between a 286-space surface lot and 364 peak-period spaces in the Building 6 garage.

What is next on the city's calendar?

The Land Use Committee is scheduled to take up the independent traffic peer review on December 8 and has another meeting planned for mid-to-late January. A full City Council vote is needed by early February to meet the MBTA deadline.

If you own a home in Lower Falls or Auburndale and want to know how the Riverside timeline could affect your sale, or you are a buyer looking at a house that faces Grove Street, the Condon Droney Team can go through the recent sales near the station with you and help you decide when to act. Start with a home valuation, and we will take it from there.